Optimized PEA
*As outlined in the news release dated June 4, 2013 – Full PEA to be published on SEDAR in late July 2013
Highlights of the June 2013 Optimized PEA:
- Large in-pit resource of 1.1 M ounces contained, and 852,700 ounces recoverable, gold
- Heap leach system averaging 80% gold recovery
- Average annual production of 76,500 ounces gold & 30,000 ounces silver &30,000 ounces silver
- Total cash cost of $778/gold ounce
- Initial capex of $101M inclusive of $36M of contingency and pre-production/indirect costs, engineering studies and permitting
- Strong leverage to gold with NPV(5%) $146.8M, 23.1% IRR and 4.7 year payback at $1300 gold increasing to NPV(5%) $469.8M, 59.2% IRR and 1.7 year payback at $1800 gold
- Does not include 2012-13 step-out exploration results in the North area and Yellow Jacket high-grade zones
- Low strip ratio of 0.53.
Base Case Gold Price Sensitivity Analysis – North Bullfrog Project
(all values in constant 2013 US$)
|
Gold Price ($/Oz)
|
NPV5% ($M)
|
NPV7.5% ($M)
|
IRR (%)
|
Payback (yrs)
|
|
$1100
|
$17.6
|
$(1.4)
|
7.3%
|
8.3
|
|
$1200
|
$82.2
|
$55.6
|
15.4%
|
6.1
|
|
$1300
|
$146.8
|
$112.6
|
23.1%
|
4.7
|
|
$1400
|
$211.4
|
$169.5
|
30.6%
|
3.4
|
|
$1500
|
$276.0
|
$226.5
|
37.9%
|
2.6
|
|
$1600
|
$340.6
|
$283.5
|
45.1%
|
2.1
|
|
$1800
|
$469.8
|
$397.4
|
59.2%
|
1.7
|
PEA Key Physical Data – North Bullfrog Heap Leach Project
|
Key Physical Data
|
Units
|
Value
|
|
Process Feed Mined
|
M tonnes
|
151.8
|
|
Overburden Mined
|
M tonnes
|
80.1
|
|
Total Material Mined
|
M tonnes
|
231.9
|
|
Mine Life
|
Years
|
11
|
|
Contained Gold
|
M Oz
|
1.07
|
|
Recovered Gold
|
M Oz
|
0.853
|
|
Recovered Silver
|
M Oz
|
0.333
|
|
Average Strip Ratio
|
Overburden/Process Feed
|
0.53
|
|
Average Gold Grade
|
g/t
|
0.219
|
|
Average Gold Recovery
|
%
|
80
|
|
Annual Process Feed Mined
|
M tonnes/yr
|
13.8
|
|
Annual Gold Produced
|
K Oz/yr
|
76.5
|
PEA Initial Capital Cost Estimate– North Bullfrog Heap Leach Project
|
Capital Area
|
Estimated Capital Cost (USD $M)
|
|
Initial Capital
|
$66.2 M
|
|
EPCM
|
$13.1 M
|
|
Contingency
|
$21.9 M
|
|
Total Initial Capital Cost
|
$101.2 M
|
|
|
|
|
Sustaining Capital
|
$108.8 M
|
|
Total LOM Capital Cost
|
$210.0 M
|
Operating Costs– North Bullfrog Heap Leach Project
|
Cost
|
Cost per Process tonne ($/tonne)
|
Cost/Recovered Gold Oz ($/Oz)
|
|
Mining
|
$2.14
|
$380
|
|
Processing
|
$1.73
|
$309
|
|
Administration
|
$0.41
|
$73
|
|
Reclamation
|
$0.09
|
$16
|
|
Total Operating Cost
|
$4.37
|
$778
|
North Bullfrog Project - Heap Leach PEA Summary
(values in 2013 USD based on a $1,300 Whittle shell, mining recoverable in-pit resources above
0.1 g/t (0.003 oz/ton) gold cut off grade)
|
Parameter
|
Summary Data
|
|
In-pit resource – Indicated
|
26.9 Mt at 0.290 g/t for 250,750 Au Oz.
|
|
In-pit resource – Inferred
|
124.9 Mt at 0.203 g/t for 816,650 Au Oz.
|
|
NPV(5%) ; IRR at USD 1,300 per Au Oz
|
USD 146.8M; 23%
|
|
Overall Strip Ratio
|
1 to 0.53 (mined mineral resource to overburden)
|
|
Average Annual Gold Production
|
76,500k Oz/year
|
|
Average Gold Recovery
|
80%
|
|
Average Cash Cost
|
USD 778/Au oz
|
|
Average Silver Recovery
|
8%
|
|
Average Total Mining Rate
|
57.7 k tonne/day |
|
Average Mineralized Material Mining Rate
|
37.8 k tonne/day
|
North Bullfrog Project – Estimated Annual Production

