Optimized PEA

*As outlined in the news release dated June 4, 2013 – Full PEA to be published on SEDAR in late July 2013

Highlights of the June 2013 Optimized PEA:

  • Large in-pit resource of 1.1 M ounces contained, and 852,700 ounces recoverable, gold
  • Heap leach system averaging 80% gold recovery
  • Average annual production of 76,500 ounces gold & 30,000 ounces silver &30,000 ounces silver
  • Total cash cost of $778/gold ounce
  • Initial capex of $101M inclusive of $36M of contingency and pre-production/indirect costs, engineering studies and permitting
  • Strong leverage to gold with NPV(5%) $146.8M, 23.1% IRR and 4.7 year payback at $1300 gold increasing to NPV(5%) $469.8M, 59.2% IRR and 1.7 year payback at $1800 gold
  • Does not include 2012-13 step-out exploration results in the North area and Yellow Jacket high-grade zones
  • Low strip ratio of 0.53.

Base Case Gold Price Sensitivity Analysis – North Bullfrog Project
(all values in constant 2013 US$)

Gold Price ($/Oz)
NPV5% ($M)
NPV7.5%  ($M)
IRR (%)
Payback (yrs)
$1100
$17.6
$(1.4)
7.3%
8.3
$1200
$82.2
$55.6
15.4%
6.1
$1300
$146.8
$112.6
23.1%
4.7
$1400
$211.4
$169.5
30.6%
3.4
$1500
$276.0
$226.5
37.9%
2.6
$1600
$340.6
$283.5
45.1%
2.1
$1800
$469.8
$397.4
59.2%
1.7


PEA Key Physical Data – North Bullfrog Heap Leach Project

Key Physical Data
Units
Value
Process Feed Mined
M tonnes
151.8
Overburden Mined
M tonnes
80.1
Total Material Mined
M tonnes
231.9
Mine Life
Years
11
Contained Gold
M Oz
1.07
Recovered Gold
M Oz
0.853
Recovered Silver
M Oz
0.333
Average Strip Ratio
Overburden/Process Feed
0.53
Average Gold Grade
g/t
0.219
Average Gold Recovery
%
80
Annual Process Feed Mined
M tonnes/yr
13.8
Annual Gold Produced
K Oz/yr
76.5


PEA Initial Capital Cost Estimate– North Bullfrog Heap Leach Project

Capital Area
Estimated Capital Cost (USD $M)
Initial Capital
$66.2 M
EPCM
$13.1 M
Contingency
$21.9 M
Total Initial Capital Cost
$101.2 M
 
 
Sustaining Capital
$108.8 M
Total LOM Capital Cost
$210.0 M


Operating Costs– North Bullfrog Heap Leach Project

Cost
Cost per Process tonne ($/tonne)
Cost/Recovered Gold Oz ($/Oz)
Mining
$2.14
$380
Processing
$1.73
$309
Administration
$0.41
$73
Reclamation
$0.09
$16
Total Operating Cost
$4.37
$778


North Bullfrog Project - Heap Leach PEA Summary
(values in 2013 USD based on a $1,300 Whittle shell, mining recoverable in-pit resources above
0.1 g/t (0.003 oz/ton) gold cut off grade)

Parameter
Summary Data
In-pit resource – Indicated
26.9 Mt at 0.290 g/t for 250,750 Au Oz.
In-pit resource – Inferred
124.9 Mt at 0.203 g/t for 816,650 Au Oz.
NPV(5%) ; IRR at USD 1,300 per Au Oz
USD 146.8M;  23%
Overall Strip Ratio
1 to 0.53 (mined mineral resource to overburden)
Average Annual Gold Production
76,500k Oz/year
Average Gold Recovery
80%
Average Cash Cost
USD 778/Au oz
Average Silver Recovery
8%
Average Total Mining Rate
57.7 k tonne/day
Average Mineralized Material Mining Rate
37.8 k tonne/day


 

North Bullfrog Project – Estimated Annual Production

 

To view the updated Preliminary Economic Assessment as outlined in December 2012 please click here.

 

*As outlined in the news release dated December 6, 2012 – Full PEA published on SEDAR found HERE

Highlights of the December 2012 PEA:

  • Initial gold production brought forward 2 years earlier targeting late 2014
  • Average annual gold production 74,800 ounces
  • 1.0M ounces contained and 765,000 ounces recoverable gold
  • Total cash cost of $816/oz gold
  • Low strip ratio of 0.48:1
  • Does not include 2012 step-out drill results in the North area and Yellow Jacket high-grade zone

Base Case Gold Price Sensitivity Analysis – North Bullfrog Project
(all values in constant 2012 US$)

Gold Price ($/Oz)
NPV5% ($M)
NPV7.5%  ($M)
IRR (%)
Payback (yrs)
$1300
$62
$38
13.0%
7.1
$1400
$119
$87
19.7%
6.3
$1479
$166
$130
26.4%
5.2
$1600
$232
$186
31.7%
4.3
$1700
$288
$235
37.3%
3.6
$1800
$345
$284
42.7%
3.2


PEA Key Physical Data – North Bullfrog Heap Leach Project

Key Physical Data
Units
Value
Process Feed Mined
M tonnes
135.7
Overburden Mined
M tonnes
64.6
Total Material Mined
M tonnes
200.3
Mine Life
Years
10
Contained Gold
M Oz
1.01
Recovered Gold
M Oz
0.76
Average Strip Ratio
Overburden/Process Feed
0.48
Average Gold Grade
g/t
0.233
Average Gold Recovery
%
75.0
Annual Process Feed Mined
M tonnes/yr
13.6
Annual Gold Produced
K Oz/yr
74.8


PEA Initial Capital Cost Estimate– North Bullfrog Heap Leach Project

Capital Area
Estimated Capital Cost (USD $M)
Phase 1 Initial Capital
$59.8 M
Phase 2 Start up
$35.4 M
Sustaining Capital
$128.3 M
 

 

Total*
$223.5 M
*adjusted for year 1 and year 2 cash contribution at base case gold price


Operating Costs– North Bullfrog Heap Leach Project

Cost
Cost per Process tonne ($/tonne)
Cost/Recovered Gold Oz ($/Oz)
Mining
$2.17
$384
Processing
$1.72
$305
Administration
$0.59
$ 106
Reclamation
$0.12
$21
Total Operating Cost
$4.60
$816


North Bullfrog Project - Heap Leach PEA Summary
(All values in 2012 USD based on a $1,300 Whittle shell, mining recoverable in-pit resources
above 0.1 g/t (0.003 oz/ton) gold cut off grade)

Parameter
Summary Data
In-pit resource – Indicated
20.8 Mt at 0.31 g/t for 209,250 Au Oz.
In-pit resource – Inferred
114.9 Mt at 0.22 g/t for 804,570 Au Oz.
NPV(5%) ; IRR at USD 1,479 per Au Oz
USD 166.2M;  26.4%
Overall Strip Ratio
1 to 0.48 (mined mineral resource to overburden)
Average Annual Gold Production
74,800k Oz/year
Average Gold Recovery
75%
Average Total Mining Rate
55 k tonne/day
Average Mineralized Material Mining Rate
37 k tonne/day


 



Projected PEA production profile for the two phase North Bullfrog project

 

 

To view the initial Preliminary Economic Assessment as outlined in February 2012 please click here.
 
To view the full version of the Preliminary Economic Assessment please click HERE.

*Based on the Company’s NI-43-101 resource estimate as published on November 7, 2011

Highlights of the PEA:
  • Low total initial capital expenditure of $68.8M
  • Average annual gold production of 57,700 ounces with an average of 70,000 ounces in the first 3 years
  • 1.1M ounces contained and 747,000 ounces recoverable gold
  • Total cash cost of $815/oz gold with an average of $673/oz gold over the first 3 years
  • Low strip ratio of 0.41:1 and less than 0.3:1 in the first 3 years


Base Case Gold Price Sensitivity Analysis – North Bullfrog Project
(all values in constant 2012 US$)
 
Gold Price ($/Oz)
NPV5% ($M)
NPV7.5%  ($M)
IRR (%)
Payback (yrs)
$1200
$63
$46
18.2%
7.3
$1300
$118
$94
28.8%
2.6
$1400
$173
$141
39.1%
2.0
$1500
$228
$189
49.4%
1.7
$1600
$283
$237
59.6%
1.4
$1700
$338
$285
69.7%
1.2

 

PEA Key Physical Data – North Bullfrog Heap Leach Project

Key Physical Data
Units
Value
Process Feed Mined
M tonnes
142.7
Overburden Mined
M tonnes
58.5
Total Material Mined
M tonnes
201.2
Mine Life
Years
12.8
Contained Gold
M Oz
1.09
Recovered Gold
M Oz
0.75
Average Strip Ratio
Overburden/Process Feed
0.41
Average Gold Grade
g/t
0.237
Average Gold Recovery
%
68.6
Annual Process Feed Mined
M tonnes/yr
11
Annual Gold Produced
K Oz/yr
57.7

 

PEA Initial Capital Cost Estimate– North Bullfrog Heap Leach Project

Capital Area
Estimated Capital Cost (USD $M)
Direct Capital Cost
$42.2
Indirect Costs
$9.1
Owner’s Cost
$5.0
Contingency
$12.5
Total Initial Capex*
$68.8
      *excludes working capital and sustaining capital

 

Operating Costs– North Bullfrog Heap Leach Project

Cost
Cost per Process tonne ($/tonne)
Cost/Recovered Gold Oz ($/Oz)
Mining
$1.97
$377
Processing
$1.67
$320
Administration
$0.50
$95
Reclamation
$0.12
$23
Total Operating Cost
$4.27
$815

 

North Bullfrog Project - Heap Leach PEA Summary
(All values in 2012 USD based on a $1,300 Whittle shell, mining recoverable in-pit resources
above 0.1 g/t (0.003 oz/ton) gold cut off grade)

Parameter
Summary Data
In-pit resource – Indicated
19.5 M tonnes @ 0.32 g/t for 199k Oz Au contained
In-pit resource – Inferred
123.3 M tonnes @ 0.23 g/t for 890k Oz Au contained
NPV(5%) ; IRR at USD 1,300 per Au Oz
USD 118.3M; 28.8%
Overall Strip Ratio
1 to 0.41 (mined mineral resource to overburden)
Avg. Annual Gold Production
57.7k Oz/year
Avg. Gold Recovery
69%
Avg. Total Mining Rate
44 k tonne/day
Avg. Mineralized Material Mining Rate
31 k tonne/day